Further to our letter on 4th of March 2014, this update is issued to confirm the time frame of works. It is confirmed that the extent of the works will be between Crossen Street and Campaspe Esplanade and the appointed contractor intends to carry out works from 1st of April to 17th of April 2014.

Location: South Side of Butcher Street from Crossen Street to Campaspe Esplanade, Echuca

Details of proposed work: Removal and replacement of concrete footpath including renewal of vehicle crossings where required.

 Note: Vehicle crossings have been identified to be replaced within this project.

The contractor will arrange the exact date of work on each vehicle crossing and you will be informed of the required arrangements prior to works starting.

Approximate duration: 3 weeks

Timing of the works is subject to change pending weather conditions. You will be advised if the targeted time frame is changed. If you wish to discuss any matters relating to these works, please contact Amir Akrami on 5481 2819.